Bushcat Build Log

  • Flap Handle Installation

    Aircraft: Bushcat 19-2226
    Task Date: 23/08/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 39
    Hours: 1.5 hrs
    Task: Fitted flap handle. Had to remove some paint on the bracket to allow the catch to engage properly in the retract position.  More...
  • Control Stick Installation

    Aircraft: Bushcat 19-2226
    Task Date: 02/08/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 37
    Hours: 3 hrs
    Task: This took longer than expected due to two of the fuselage bracing tubes being incorrectly fitted.After refitting them correctly the control stick could be installed. Torque seal and Loctite were …  More...
  • Rudder Pedal Linkage

    Aircraft: Bushcat 19-2226
    Task Date: 02/08/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 36
    Hours: 0.5 hr
    Task: Fitted linkage to rudder pedals. Loctite was used on the bolts.  More...
  • Matco Wheel Assembly

    Aircraft: Bushcat 19-2226
    Task Date: 02/08/2025
    Builder: Malcolm Hardy & Thomas Hardy
    Category: Landing Gear
    Section: 29
    Hours: 0.5 hr
    Task: Wheels were already assembled.We greased the tapered bearings then fitted the wheels and brake calipers.The wheel nuts were tightened according to the Matco instructions.  More...